The TCEQ requires at least ________. | 1 mg/L residual after 20 minute contact | 100%
|
How many minutes of detention time should a chlorine contact chamber have at peak flow? | 20 minutes | 100%
|
Chlorine may be used for which of the following? | All of the above | 100%
|
Disinfection may also be accomplished by which of the following? | All of the above | 100%
|
Chlorine is available as which of the following? | All of the above | 100%
|
Forms of chlorine used in wastewater treatment include which of the following? | All of the above | 100%
|
Chlorine combines with ammonia in wastewater to form ________. | chloramines | 100%
|
Which of the following is a good disinfectant? | Chlorine | 100%
|
At 20°C the HOCl concentration will vary with the pH as follows ________. | pH 7: 80% HOCl | 100%
|
Chlorine equipment shall be capable of which of the following? | All of the above | 86%
|
Chlorine could be used as an aid in trickling filter operation to ________. | breakup a ponding problem | 86%
|
When gas chlorine is added to water, which of the following is formed? | HOCl AND CaCl2 | 86%
|
Gas chlorination facilities should be equipped with a ________. | bottle of ammonium hydroxide | 71%
|
If a chlorine dosage of 12 mg/L is added to a wastewater effluent containing ammonia and the chlorine demand is 11.5 mg/L, the residual would be which of the following? | Sufficient AND a monochloramine | 71%
|
The TCEQ allows the reuse of treated wastewater for which of the following? | All of the above | 57%
|
Because UV Light is not a chemical, it ________. | does not alter the physical properties of the water | 57%
|
Reclaimed water piping must be color-coded ________. | purple | 43%
|
Reclaimed water providers must report monthly to TCEQ the ________ and ________ of reclaimed water delivered to a user | volume/quality | 29%
|